CONSTRUCTION SITE NEWS

30. März 2023

SUCCESSFUL START TO THE FINAL YEAR OF CONSTRUCTION!

Once the shell has been completed, work continues on the outer shell and the installation of the building services.

Things have been running smoothly since the beginning of the year, just like in the first year of construction. Deadlines and costs are on schedule. The "good & dry weather" - for construction - has played a part in this.
Last week, the complete exterior walls were erected within 4 days. The windows are now being fitted to these wooden elements, as is the exterior formwork in wood.
The roofs are now being sealed. With the external doors, which will be installed in around three weeks, the outer shell can be sealed - another important step.
Inside the building, plumbers from plumbing, heating, cooling and ventilation are working with muscle power on the pre-assembly of the installations. Some pipes are being laid and fitted with sleeves!
With the 13 holes for the geothermal probes (from mid-March) and the subfloors (from mid-April), two further important stages are on the agenda - before the big final spurt of the complete interior construction and the surrounding work begins!
We wish all craftsmen continued enjoyment at work and accident-free working days!
#story
#storythusis
#remainsinmemory
#whatsyourstory

Privacy settings

For an optimal website experience, we use cookies and other online technologies to display personalized content, offer functions and collect statistics. Your click on "Accept" allows us to process this data and pass it on to third-party providers (including in third countries) in accordance with our privacy policy. Cookies can be rejected at any time or adjusted in the settings.

Cookie Policy

Privacy settings

This tool helps you to select or deactivate various tags, trackers and analysis tools on this website.

Cookie Policy